Concrete worked example: 6 m x 4 m slab, 100 mm deep

BuildTrue concrete pack. Estimates only. This example uses the same formulas as the concrete calculator on the pack page and the standalone BuildTrue concrete estimator. Verified by hand, step by step, below.

Inputs

InputValue
Slab length6 m
Slab width4 m
Slab depth100 mm (0.100 m)
Waste allowance10 percent
Bag yield, stated assumptionOne 30 kg pre-mix bag yields about 0.0135 cubic metres
Conversion, stated1 cubic metre = 1.30795 cubic yards

Step by step arithmetic

  1. Volume before waste:

6 x 4 x 0.1 = 2.40 cubic metres.

  1. Volume with waste:

2.40 x (1 + 10 / 100) = 2.40 x 1.10 = 2.64 cubic metres.

  1. Volume in cubic yards:

2.64 x 1.30795 = 3.453 cubic yards, shown as 3.45 cubic yards. Before waste: 2.40 x 1.30795 = 3.139 cubic yards, shown as 3.14.

  1. Bags:

2.64 / 0.0135 = 195.5556 bags. Round up with the epsilon safe ceiling: 196 bags. Sanity check: 195 bags x 0.0135 = 2.6325 cubic metres, which is short of 2.64. 196 bags x 0.0135 = 2.646 cubic metres, which covers it. So 196 is the smallest whole bag count that works.

Purchasable counts

ItemRaw resultBuy
30 kg pre-mix bags195.56 bags196 bags
Ready-mix alternative2.64 cubic metres with wasteOrder to the supplier increment above 2.64 cubic metres. If the supplier sells in 0.5 cubic metre steps, that is 3.0 cubic metres. Confirm the increment, the minimum load, and any short load fee before pour day

Sample material list for this job

ItemSpecificationQuantity
Pre-mix concrete30 kg bags, 0.0135 cubic metres yield each196 bags (or ready-mix as above, not both)
Granular baseCompacted depth as specifiedVolume from base area and compacted depth, ordered separately
ReinforcementRebar or mesh as specifiedPer layout, with laps. Not counted by the slab calculator
Form lumber and stakesTo suit 100 mm depth and 20 m of perimeter (6 + 4 + 6 + 4)Perimeter run plus bracing
Curing and joint consumablesAs specifiedPer label coverage

Perimeter check used in the list: 6 + 4 + 6 + 4 = 20 m of form run.

Notes and limits